Avesoro NEW LIBERTY BALL MILL FOUNDATIONS
Mar 18 2014· The completion of the ball mill foundations is a major achievement and is a key milestone in the overall New Liberty project construction schedule The pouring of concrete for the ball mill foundations was completed using a continuous pour undertaken between Wednesday 5 March and Sunday 9 March 2014